On June 29, an interpersonal conflict took place among workers at the 3GP construction site causing several injuries of contractor employees. Medical assistance was provided to more than 40 workers at TCO clinics for non-life threatening injuries.

The situation is stable as of now and TCO continues to work closely with law enforcement bodies, government authorities and contractor companies to ensure the safety and well-being of the personnel at Tengiz.

Local police have initiated an investigation and will maintain a presence for as long as necessary.

Work at the 3GP construction site has been temporarily suspended and TCO is assessing the appropriate time to resume activities. Other TCO facilities are operating as normal.